Permitting Process & Timeline
What is the permitting process?
The Hospitals filed a project application with the City of Palo Alto in August 2007 and the project will proceed through the normal entitlement process, which includes many opportunities for public input and environmental review. Upon approval from the City, the plans will subsequently be submitted to the Office of Statewide Health Planning and Development (OSHPD) for review. The Hospitals are planning for additional community outreach as the project planning and design is developed.
Will an EIR be conducted?
Yes. The Draft Environmental Impact Report (DEIR) is expected to be complete by spring 2010 and the final Environmental Impact Report (EIR) will follow. The Palo Alto City Council could take action on the project application in fall 2010. For more information on the permitting process or the EIR, please visit the City of Palo Alto’s website.
What was the connection to the Stanford Shopping Center expansion project?
In April 2009, Stanford University withdrew Simon Properties’ proposal to expand the Stanford Shopping Center. The Shopping Center Project and Renewal Project were not linked in any way other than being studied in the EIR. Our primary concern and mission is to ensure that the Medical Center is fully compliant with new seismic standards and is able to meet the current and future needs of our community.